Duration: 2025 - 2027
Client: PTSC
Scope of work: T05 Package: Installation and completion of boiler structural steel works: 10,054 tons; Installation and completion of boiler body: 6,790 tons; - T37 Package: Installation of ESP system; Equipment: 1,080 tons; Structural steel: 280 tons; Insulation: 32,800 m²; Electrical and control equipment: 286 tons. Installation of FGD system; Equipment: 1,795 tons; Structural steel: 1,666 tons; FGD area flue/air ducts and accessories: 1,530 tons; Piping: 493 tons; Tanks and vessels: 324 tons; Electrical and control equipment; Insulation: 17,096 m². EPC design, supply, and installation of HVAC system for ESP & FGD systems. EPC design, supply, and installation of communication system for ESP & FGD systems.
Duration: 2025 - 2027
Client: CO2 Product
Scope of work: Engineering, supply, and construction (EPC) of a high-tech CO₂ production plant with a capacity of 100,000 tons/year; Piping system: 12,808 ID; CO₂ storage tanks: 1,425 tons; Structural steel: 92 tons; Equipment: 1,578 tons; Civil works; Electrical and control systems; Auxiliary systems; Pre-commissioning, commissioning, and handover.
Duration: 2026 - 2027
Client: PQPOC / PTSC M&C
Scope of work: Fabrication of Link Bridges and Deck Support Frames (DSF) for the Central Processing Platform of Block B Gas project; Total weight: 2,719 tons.
Duration: 2025 - 2027
Client: SWPOC / PTSC- SMP
Scope of work: Fabrication and installation (SMP) of structural, mechanical, and piping works for O Mon Station, LBV 06, and An Minh LFS; Structural steel: 662 tons; Process and firefighting piping: 58,000 ID; Equipment: 660 tons.- Pipeline package: Installation of pipeline from LBV05 to O Mon GDC; Pipeline length: 12.12 km; Total piping quantity: 30,960 ID.- FOC package: Installation of fiber optic cable and communication equipment for the pipeline system; HDPE D40 conduit: 200 km; 16-core armored single-mode fiber optic cable (G.652): 220 km; Junction boxes: 110 units.
Duration: 2026
Client: PVFCCo / PTSC
Scope of work: Engineering, procurement, and construction (EPC) of a 2,400 m³ H₃PO₄ acid tank, centrifugal pumps, process piping system, firefighting piping system, and electrical/control systems.
Duration: 2025 - 2026
Client: Technical Commercial and Investment Corporation – JSC
Scope of work: Engineering, procurement, and construction (EPC) of 04 petroleum storage tanks with a capacity of 10,000 m³ each; 01 fire water tank with a capacity of 1,500 m3, totaling approximately 1,185 tons of materials; 01 centrifugal pump with a capacity of 400 m3/h, 03 centrifugal pumps with a capacity of 100 m3/h each, and 01 gear pump with a capacity of 100 m3/h; process piping system, firefighting piping system, and truck loading arms.
Duration: 3/2023 - 7/2023
Client: Anh Phat Corporation
Scope of work: Electrical & Intrusment: Installation for Earthing system; Installation for Cable tray, conduit; Installation and conection for MOV; Process loop test and commissionin
Duration: 2022 - 2023
Client: NSRP
Scope of work: Procurement, Fabrication, Construction, Installation and Commissioning for Cleaning Bay
Duration: 2023 - 2024
Client: Orsted Taiwan Ltd/PTSC
Scope of work: Fabrication total 24 Suction Bucket; Total Volume: ~7000 ton for Suction Bucket fabrication
Duration: 2019
Client: Viet Nhat Gas JSC
Scope of work: Installation of gas storage tanks and vaporizers; above-ground welding for Oxygen and Argon pipeline systems; and chemical cleaning of the piping system
Duration: 2014 - 2015
Client: NSRP
Scope of work: Fabrication for pile connection of NSRP Jetty: about 14 tons, 52,475 ID pile F914 x 18 and F813 x 16
Duration: 2019
Client: TPSK/PTSC
Scope of work: Engineering, procurement, and construction of 08 storage tanks with a total capacity of approximately 7,000 m³ and a total weight of nearly 400 tons; shop fabrication of piping: 149,000 IDs; field installation of piping: 132,000 IDs; pipe support structures: 230 tons; painting works: 45,000 m²; steel structures: 2,700 tons; equipment installation: 3,000 tons; and piping system testing
Duration: 2014 - 2016
Client: NSRP/PTSC M&C
Scope of work: workshop fabrication around 40.000 DI for pipe spool, pipe supports, fittings, pipe rack, structure, etec and painting 90.000 m2.
Duration: 2015 - 2017
Client: NSRP/PTSC Power
Scope of work: Painting 35.000 m2 and wrapping 2.200 m2 work for piping, pipe support, fitting, etc and underground pipeline.
Durant: 2014 - 2016
Client: NSRP
Scope of work: Fabrication, installation, and hydrostatic testing of underground piping system. Scope of work: 150 piping IDs, with a total hydrotest volume of 780,000 IN-M
Duration: 2022
Client: Anh Phat Corporation
Scope of work: Construction and installation of five 12-inch and 14-inch pipelines from Nghi Son Refinery and Petrochemical Plant to Anh Phat Petroleum Depot, with a total length of 1.5 km.
Duration: 2019 - 2020
Client: TOP Solvent Vietnam Co., Ltd
Scope of work: Procurement of materials, fabrication and final coating of 127 IBC chemical storage tanks, packaging, transportation, and handover at Hai Phong Port Plant and Go Dau Plant
Duration: 2019
Client: PTSC M&C
Scope of work: Fabricate Stair towers, WHRU exhaust support and GTC exhaust support for Sao Vang Dai Nguyet Project. Total fabricated quantity: 205 tons.
Duration: 2018
Client: Top Solvent (Vietnam), Thai Oil Group.
Scope of work: Engineering design and execution, procurement, construction, commissioning, and handover of 04 petrochemical product storage tanks (7,000 m³ each) and 02 mixing tanks (200 m³ each); piping systems; pumping equipment, drum handling machines, loading arms, and control systems; warehouse facilities; office building and security station; electrical, control, and fire protection systems, along with associated civil works.
Duration: 2019 - 2020
Client: Vopak (Vietnam) Co., Ltd - Vopak Group.
Scope of work: Engineering, procurement, construction, commissioning, and handover of 11 chemical storage tanks with a total capacity of 20,000 m³ and total weight of 720 tons; more than 30,000 piping IDs; pumping systems; equipment; and control systems.
Duration: 2018
Client: Top Solvent (Vietnam), Thai Oil Group
Scope of work: EPC works for Extension of Storage Tanks (03 tanks for chemical/ solvent storage with total capacity of 6,000 m3 (03 tanks x 2,000m3), pipeline system.
Duration: 2017
Client: Anh Phat Coporation
Scope of work: Procurement and Contruction for 4 warehouses (03 warehouses 40m x 80m and 01 warehouse 40m x 64 m)
Duration: 2017 - 2019
Client: PVN/PTSC
Scope of work: installation ESP, FGD system, total weight 5,600 ton